Construction works at the site are continuing at an active pace. A grounding connection has been welded to each steel column—an important engineering measure that enhances the overall safety of the building in compliance with current construction standards.
A layer of roofing felt is being applied over the floor slabs as a waterproofing…
Construction is progressing actively and according to schedule. Our team is carrying out a full scope of works related to the future pool area. All necessary installations for the pool, terrace, and technical zone have been completed — the piping has been laid, service routes prepared, and connection points installed.
At the same…
We have successfully completed the pouring of the final floor slab of our building and can now move on to the construction of the rooftop swimming pool.
Before pouring the pool basin, our specialists are installing a layer of thermal insulation. This system prevents condensation and eliminates the risk of moisture in the apartments located…
Construction works at the site are actively progressing. The pouring of the current floor has been completed — the monolithic structures have been successfully formed and passed quality inspection. Specialists are now preparing the site for pouring the slab of the final floor.
Brick deliveries have already begun at the construction site for…
Work on the next floor of the building is well under way on site. The team has completed the formwork and carefully bonded the rebar, providing a solid foundation for the future slab.
Once the structures have been prepared, the concrete is poured - the key stage that forms the monolithic slab.
In parallel,…
After the reinforcement was completed, the slabs, staircases, and elevator shaft were poured.
The staircases in our project are constructed using monolithic casting, which distinguishes them from traditional masonry construction. This technology makes the steps solid and durable, significantly increasing their strength, reliability, and resistance to wear.
The elevator shaft is constructed floor by…
Reinforcement of the slabs, a key stage in monolithic construction, has been completed on site. Special blocks have been installed in the formwork, followed by the placement and tying of the reinforcement.
The quality of the reinforcement has a direct impact on the overall strength of the building, so special attention was paid to the…
We have completed an important stage - the installation of formwork and the pouring of reinforced concrete columns.
In parallel, the elevator shaft is being constructed floor by floor, step by step, with the strictest possible adherence to technology.
The formwork for the first floor slab has already been prepared and…
A batch of metal columns arrived at the site - we started unloading and installing them on two floors at once. This technology allows us to speed up construction and ensure maximum strength of the supporting frame. The columns are securely fixed to the formwork and then the structures are welded.
Special attention…
The construction works on the construction site continue - tying of reinforcement and laying of engineering communications under the building foundation.
The reinforcement is knitted by hand from the bottom floor to create a solid and sturdy frame grid for reinforced concrete structures. This approach is designed to be resistant to loads and seismic effects.…