The holiday period is behind us, and construction work on site is continuing at a regular pace. At the moment, the walls are being constructed across the entire building. The main façade is almost complete, with the building envelope approximately 80% closed, while the internal walls are about 60% finished, allowing us to proceed with the next stages of work.


Inside the building, the installation of sound insulation is already underway—an important element of comfort that directly affects the quality of life in the future home. All processes are being carried out under the strict supervision of the lead architect and the technical architect.