We have completed an important stage - the installation of formwork and the pouring of reinforced concrete columns.
In parallel, the elevator shaft is being constructed floor by floor, step by step, with the strictest possible adherence to technology.
The formwork for the first floor slab has already been prepared and…
A batch of metal columns arrived at the site - we started unloading and installing them on two floors at once. This technology allows us to speed up construction and ensure maximum strength of the supporting frame. The columns are securely fixed to the formwork and then the structures are welded.
Special attention…
The construction works on the construction site continue - tying of reinforcement and laying of engineering communications under the building foundation.
The reinforcement is knitted by hand from the bottom floor to create a solid and sturdy frame grid for reinforced concrete structures. This approach is designed to be resistant to loads and seismic effects.…
On 14 June 2025, the demolition phase of the old building was officially completed, and we moved on to the next important stage – excavating a 40 cm-deep trench. At this stage, we are also collecting soil samples for geological testing, which are necessary to assess the load-bearing capacity of the soil and to further…
We have officially started our construction project: the site at CalleAngustias, 18, 29780 Nerja, Malaga, Spain, is actively being demolished. All necessary fencing has already been installed in front of the construction site, a pedestrian safety zone has been set up and the road surface has been protected from possible mechanical and other damage. …
We are pleased to announce that the Vida Del Mar residential project received its official building license in April 2025.
CARTA-ICIO-1
LICENCIA-DE-OBRAS
This is an important milestone that paves the way for the launch of the project in the heart of Nerja, on the Costa del Sol. Construction work is scheduled to start in the coming…