We have completed an important stage - the installation of formwork and the pouring of reinforced concrete columns.
In parallel, the elevator shaft is being constructed floor by floor, step by step, with the strictest possible adherence to technology.
The formwork for the first floor slab has already been prepared and…
A batch of metal columns arrived at the site - we started unloading and installing them on two floors at once. This technology allows us to speed up construction and ensure maximum strength of the supporting frame. The columns are securely fixed to the formwork and then the structures are welded.
Special attention…
The construction works on the construction site continue - tying of reinforcement and laying of engineering communications under the building foundation.
The reinforcement is knitted by hand from the bottom floor to create a solid and sturdy frame grid for reinforced concrete structures. This approach is designed to be resistant to loads and seismic effects.…